INSTALLATION PROCEDURE

Home / INSTALLATION PROCEDURE

At site, the poles can be erected on footing foundation or on pile foundation; depending upon the type of soil and water table. If it is lighter than traditional BW (approximately 1/3 in weight) the size of footing can be taken less.

After concrete gets strength, the joints between foundation and pole(Generally 48 hrs) the panels will be fixed between two poles in tongs and groove fashion. The Panel Will be fixed40mm – 40mm between Two Poles In Groov of Poles. The joints between two panels and the gape between pole and panel will be filled with rich cement mortar.